Training for this procedure can be found in these courses:
STANDARD OF PERFORMANCE
Expansion valve must be located and installed according to manufacturer’s specifications and job specifications. Valve must be specified size and capacity for system. It must meter refrigerant to meet evaporator requirements and provide desired refrigerant superheat. Valve connections must not leak. Applicable safety procedures must be followed.
PROCEDURE GUIDE
a. Disassembled and reassembled if required.
b. Directed flame away from main body during soldering.
c. Used heat-trap paste as needed.
8. Remove safety and protective equipment and apparel.
9. Gather tools, equipment and leftover materials, and leave work site clean.
10. Test for leaks when refrigerant circuit has been completed, and make required repairs.